Starting on July 2, 2024, the Radnor Township Public Works Department will begin roadside clearing throughout the Township. New equipment will be used including the Holland Tractor with a power arm attachment to clear overgrown vegetation including high grass/weeds, saplings, etc.
A shadow vehicle with an arrow board will follow the heavy equipment to notify oncoming traffic of the roadside work ahead and to as an extra safety measure.
The project includes all Radnor Township Wards and will begin with Ward 1 and move throughout the Township in chronological order by Ward.
Work will begin at 9am daily and each Ward should take approximately 1 week to complete.